This website uses cookies. By continuing to browse the site you agree to our use of cookies. Find out more about the cookies we use and how to manage them.

Close

Saddleback and Marradong Alumina. Western Australia. Australia

Client
BHP Billiton Worsley Alumina Pty Ltd
Sector
Mining & Natural Resources
Services
Infrastructure ConstructionBuilding Construction
Duration
Completed in 2011

Saddleback and Marradong Alumina. Western Australia. Australia

Saddleback and Marradong Alumina. Western Australia. Australia

Full project details

Laing O’Rourke completed this project in 2011 in Western Australia’s southwest for BHP Worsley. Its primary aim was to provide access to additional ore bodies north of the Marradong Mine by extending the conveyor. A primary crushing building and equipment was constructed at the Marradong site, with a short conveyor to a secondary crusher and then a 10.5 km overland conveyor to the stockpile at Saddleback.

Laing O’Rourke was engaged to supply construction labour and plant. Marradong construction works included a plant conveyor, overland conveying and miscellaneous support facilities. The secondary works at Saddleback included crushing, stockpiling and reclaiming facilities, a feed bin and plant conveyors. All materials and equipment were free-issued with the exception of items identified during construction, which Laing O’Rourke then sourced and supplied.

The overland conveyor crosses Marradong Brook along a 270 m series of raised gantries. Ore is reclaimed from the stockpile through a reclaim chamber and conveyor tunnel. The reclaim conveyor then takes the ore to a feed bin over an existing conveyor, which was also modified as part of the project.

Bulk earthworks were carried out by another contractor on site, with Laing O’Rourke performing the detailed earthworks, concreting, structural works, piping, mechanical works and electrical works, excluding commissioning.

The completed works provide additional processed ore to meet the increased capacity of the Worsley Process Plant. The project has also extended the life of the mining facility.

Project facts

Laing O’Rourke supplied construction labour and plant for the cost-reimbursable project

Works included a primary crushing building at Marradong and a 10.5 km overland conveyor to Saddleback

Laing O’Rourke performed earthworks, concreting, and structural, mechanical, piping and electrical works

Increased the capacity and extended the life of the mining facility

Featured projects

Airly Coal Mine Expansion Materials Handling and Rail Loop

New South Wales, Australia. Australia

Discover

Blackwater Coal Handling Plant

Discover

Curragh North Materials Handling System

Queensland. Australia

Discover
See all of our projects